Sourcing steam turbines from China
Steam and other vapour turbines from China, including back-pressure and condensing turbines for industrial power and heat, and rotors and blades, pay 0% UK duty on all seven lines with no anti-dumping duty. Guaranteed output and efficiency at your steam conditions decide the value. Cambridge China Bridge sources turbines.
Industrial steam turbines for power generation and combined heat and power, back-pressure and condensing turbines, blades and rotors from China pay 0% UK duty.

0% duty
Read from the UK Trade Tariff on 27 September 2026, steam turbines and other vapour turbines, heading 8406, carried 0% on goods from China on all seven lines, above and below 40 MW, including rotors, blades and other parts, with no anti-dumping measure.
Gas turbines are in heading 8411 (see our gas turbines guide), boilers under 8402 (see our steam boilers guide), and generators separately as electrical machines. Confirm the commodity code for each part of a package.
| Goods | Commodity code | Duty | Anti-dumping duty on China |
|---|---|---|---|
| Turbines for marine propulsion | 8406 10 00 00 | 0% | None |
| Other turbines of an output over 40 MW | 8406 81 00 90 | 0% | None |
| Other turbines of an output not over 40 MW | 8406 82 00 90 | 0% | None |
| Stator blades, rotors and their blades | 8406 90 10 00 | 0% | None |
| Other parts | 8406 90 90 00 | 0% | None |
Specification and safety
Steam turbines are machinery under the Supply of Machinery (Safety) Regulations 2008, and the steam piping, valves and vessels around them fall under the UK pressure equipment rules, which the plant designer addresses. IEC 60045-1 sets out the specification for steam turbines, including the information the buyer and supplier exchange and the performance guarantees.
Overspeed protection, trip valves and control systems are safety-critical, so ask for their design basis and test records before the turbine ships.
Specifying a turbine
Specify rated output, inlet steam pressure and temperature, exhaust or extraction pressures, steam flow, speed and gearbox, back-pressure or condensing type, guaranteed heat rate or efficiency, governor and protection systems, generator interface, lube oil system, and the site installation, commissioning and training package.
Worked duty example
An invented example rather than a quote: one 5 MW condensing steam turbine, commodity code 8406 82 00 90, bought for £1,400,000 free on board, with £45,000 of freight and insurance, so £1,445,000 is the value customs works from. No duty is due on steam turbines; import VAT at 20% of £1,445,000 is £289,000. If you are VAT-registered, that VAT is normally reclaimable. See calculating UK import duty and VAT for the method.
Inspection checklist
Rotor and blading: check rotor forging certificates, blade material certificates and the rotor balancing record, and witness the overspeed test where the builder performs one.
Casing and valves: check pressure test records for the casing and valves, and check the trip and control valve functions on the test bench.
Performance and documents: agree the performance test method, such as the procedure in the contract based on IEC 60045-1, and check the declaration of conformity, manuals, drawings and spares list before shipment.
What goes wrong
Steam turbines fail on performance guarantees, protection systems and support. Output or heat rate falls short at your steam conditions, overspeed and trip systems lack test evidence, lube oil systems leak, and specialist service engineers are hard to arrange.
Put performance guarantees and test methods in the contract, witness factory tests, and plan commissioning and long-term support. See our quality inspection guide.
Cambridge China Bridge sources steam turbines and turbine parts for UK and overseas energy and process plants, checking the builder's references and test facilities before an order. See factory verification.
Frequently asked questions
What is the UK import duty on steam turbines from China?
Read from the UK Trade Tariff on 27 September 2026, steam turbines up to 40 MW (8406 82) carried 0% from China, as did larger turbines and parts.
Are gas turbines the same heading?
No. Gas turbines are classified under heading 8411.
Which standard covers steam turbine specifications?
IEC 60045-1 sets out steam turbine specifications and guarantees.
Is there anti-dumping duty?
No line of heading 8406 had a UK anti-dumping measure on 27 September 2026.