Boiler superheaters and their identifiable parts from China carry 0% UK import duty across the relevant lines. Confirm with the relevant authority how the equipment's pressure, volume and fluid affect the applicable pressure equipment conformity assessment; agree the assessment route and pressure test records before ordering. Cambridge China Bridge sources boiler superheaters.

Boiler superheater duty and classification
Heading 8404 covers auxiliary plant for boilers of headings 8402 or 8403, including superheaters, and parts. Complete superheater auxiliary plant falls under 8404 10 00 00; identifiable parts fall under 8404 90 00 00. The table separates buying descriptions within these shared tariff lines.
Read from the UK Trade Tariff on 1 October 2026, both relevant lines carried 0% duty for goods from China. The supplied tariff records show no anti-dumping or countervailing measures, suspensions or attached import controls for these lines. Import VAT is separate from customs duty.
Confirm the supplied condition, intended boiler and whether the shipment is complete plant or parts using the commodity code guide. For the wider heading, see economisers and boiler auxiliary plant.
| Goods | Commodity code | Duty | Anti-dumping or countervailing duty on China |
|---|---|---|---|
| Boiler superheaters supplied as complete auxiliary plant | 8404 10 00 00 | 0% | None |
| Replacement tube banks identifiable as boiler superheater parts | 8404 90 00 00 | 0% | None |
Specify the steam duty and tube-bank layout
Give the maker the steam flow, inlet and required outlet temperatures, operating and design pressures, and flue-gas conditions. Agree tube material, wall thickness, bend geometry, header layout, connection positions, supports and access for cleaning. For replacement equipment, supply approved interface drawings rather than relying on photographs.
Confirm with the relevant authority how pressure, volume and fluid affect the applicable requirements under the Pressure Equipment (Safety) Regulations 2016. Agree the applicable conformity assessment, declaration of conformity and pressure test records. CE marking remains recognised indefinitely in Great Britain. Match the marking route and supporting documents to the actual equipment; ask for testing and certification support where needed.
Worked duty example
Illustrative example, not a quote: Two boiler superheater assemblies, illustrative order only under 8404 10 00 00, invoiced at £64,000 free on board, with £5,000 of freight and insurance to the UK. The customs value is £69,000. Duty at 0% is £0. Import VAT at 20% is charged on the customs value plus duty, £69,000, so it is £13,800. With no duty, the only import tax is the VAT, which a VAT-registered importer can usually reclaim. The import duty and VAT guide explains each step.
Inspection checklist
Materials: check tube and header certificates against the agreed grades, component markings and manufacturing records.
Welds and tests: compare weld maps, welder qualifications, non-destructive testing reports and pressure test records with the agreed inspection plan.
Fit: measure connection positions, tube-bank dimensions and support locations against approved drawings before shipment and check for distortion on arrival.
Documents and packing: match the nameplate and declaration to the supplied assembly; check tube-bank bracing, capped connections and transit damage. Use the quality inspection guide to plan checks.
Working out your own order? Send us the product on WhatsApp and we reply the same working day: WhatsApp us
What goes wrong
A replacement can match the overall dimensions yet have misplaced connections or supports. Material certificates may not trace to the delivered tubes, weld reports may omit joints, and pressure documentation may describe a different assembly. Resolve drawing and record discrepancies before releasing the shipment.
On arrival, check for bent tubes, displaced bracing, damaged connection faces and opened protective caps. Record defects against the packing list and approved drawings, and obtain the boiler engineer's acceptance of any proposed repair.
Cambridge China Bridge sources these products for UK businesses, checking the factory and the documents before shipment. See factory verification. For machinery and equipment, see machinery imports.
Frequently asked questions
What is the UK import duty on boiler superheaters from China?
The supplied tariff records show 0% on complete auxiliary plant under 8404 10 00 00 and identifiable parts under 8404 90 00 00, with no anti-dumping or countervailing measure.
Do boiler superheaters need pressure equipment documents?
Confirm with the relevant authority how pressure, volume and fluid affect the applicable requirements. Agree the conformity assessment route and obtain the declaration of conformity and pressure test records for the supplied assembly.
Can a boiler superheater use CE marking in Great Britain?
CE marking remains recognised indefinitely for pressure equipment in Great Britain. Check the applicable assessment route and supporting documents for the supplied equipment.
What should I send a factory for a replacement superheater?
Send approved connection and support drawings, tube and header specifications, steam duty, design conditions and the inspection plan. Identify which existing components will be retained.