Boiler deaerators classified as boiler auxiliary plant under heading 8404 carry 0% UK duty from China, as do dedicated parts. Pressure equipment conformity assessment depends on the equipment's classification, so agree the compliance route before ordering. Cambridge China Bridge sources boiler deaerators.

Written by Bono Xu, Founder, Cambridge China Bridge · 3 min read · Updated 2026-10-24

Aisles of a large supermarket seen from above, shelves fully stocked

Duty on boiler deaerators and dedicated parts

Heading 8404 covers auxiliary plant for boilers of heading 8402 or 8403, steam or other vapour power-unit condensers, and parts. For this guide, the relevant lines are boiler auxiliary plant and dedicated parts. The table repeats those codes for different deaerator configurations and replacement components.

Read from the UK Trade Tariff on 24 October 2026, all supplied lines carried 0% duty for goods from China. The supplied tariff record lists no anti-dumping or countervailing measures, suspensions or attached import controls. Import VAT is separate from duty.

Confirm the commodity code using the drawings, boiler application and shipment contents. Do not assume separately supplied pumps, valves or general-purpose components share the deaerator's code. See the wider boiler auxiliary plant guide and the import duty and VAT guide.

UK duty on these lines for goods of Chinese origin (one code per row), read from the UK Trade Tariff on 24 October 2026.
GoodsCommodity codeDutyAnti-dumping or countervailing duty on China
Spray-type boiler feedwater deaerators8404 10 00 000%None
Dedicated replacement deaerator trays8404 90 00 000%None

Specify feedwater duty and the pressure boundary

Specify feedwater flow, incoming water temperature, steam supply conditions, operating pressure and the residual dissolved oxygen performance you want guaranteed. Define the operating range, sampling point and acceptance test conditions. State whether you need a spray or tray arrangement, an integrated storage vessel, controls and insulation.

Agree vessel materials, corrosion allowance, design pressure and temperature, connection positions, supports, access openings and replacement internals. Request approved drawings, a weld inspection plan and pressure-test records. For pressure equipment, conformity assessment depends on classification; ask the supplier to explain the route for the exact assembly. CE marking remains recognised in Great Britain where the applicable requirements are met.

Worked duty example

Illustrative example, not a quote: Two boiler deaerators, illustrative order under 8404 10 00 00, invoiced at £64,000 free on board, with £5,000 of freight and insurance to the UK. The customs value is £69,000. Duty at 0% is £0. Import VAT at 20% is charged on the customs value plus duty, £69,000, so it is £13,800. With no duty, the only import tax is the VAT, which a VAT-registered importer can usually reclaim. The import duty and VAT guide explains each step.

Inspection checklist

Materials and welds: match material certificates to the vessel and internals; review weld maps and non-destructive test records against the agreed inspection plan.

Performance: agree a witnessed test of dissolved oxygen performance under the specified water flow, temperature and steam conditions; inspect spray distribution or tray installation.

Fit and arrival condition: compare flange positions, supports and access clearances with approved drawings; check for distorted internals, damaged coatings and moisture inside capped connections.

Documents: match the nameplate, serial identification, applicable declaration of conformity and pressure-test records to the delivered assembly. Arrange quality inspection against the agreed specification.

Working out your own order? Send us the product on WhatsApp and we reply the same working day: WhatsApp us

What goes wrong

A deaerator can fit the boiler house yet miss the agreed oxygen performance because the available steam conditions differ from the supplier's test conditions. Poor spray distribution, incorrectly installed trays and unsuitable vent arrangements are points to investigate. Require a performance guarantee tied to your operating conditions.

Connection mismatches, inaccessible internals and incomplete pressure documentation can delay installation. Resolve drawing discrepancies before fabrication and inspect the internals before closure. Use factory verification to assess whether the supplier makes and tests the vessel itself.

Cambridge China Bridge sources these products for UK businesses, checking the factory and the documents before shipment. See factory verification. For machinery and equipment, see machinery imports.

Frequently asked questions

What is the UK import duty on boiler deaerators from China?

The supplied tariff record shows 0% for boiler auxiliary plant under 8404 10 00 00 and dedicated parts under 8404 90 00 00, with no listed anti-dumping or countervailing measures.

Does a boiler deaerator need pressure equipment assessment?

For equipment within the pressure equipment rules, the conformity assessment procedure depends on its classification. Ask for the classification and supporting documents for the exact assembly.

Should I specify spray or tray deaeration?

Ask the supplier to justify the arrangement against your feedwater flow, inlet temperature, steam conditions and required dissolved oxygen performance. Include access for cleaning and replacement internals.

What should I check when the deaerator arrives?

Check connection positions, vessel and internal damage, capped openings, nameplate identification, material certificates and pressure-test records against the approved drawings and inspection plan.

Sources

  1. UK Trade Tariff — commodity codes and duty
  2. HSE pressure equipment safety guidance
  3. Pressure Equipment (Safety) Regulations 2016: Great Britain

Monthly email

What changed for UK buyers from China, and when to act

One email at the start of each month. Every figure has an official source.

One email a month. Unsubscribe with one click. Privacy

Discuss your sourcing project

Tell us the product, quantity and destination. Our own staff in China verify factories, follow production and inspect before shipment. We reply the same working day to confirm receipt and arrange next steps.

Discuss your sourcing project
Get a quote