Freeze the specification, buying basket and baseline before negotiation. Compare like-for-like costs, then count only savings supported by supplier-accepted orders, accepted goods and paid invoices. Report unused offers and avoided increases separately. Ask for this evidence pack from Cambridge China Bridge.

Written by Bono Xu, Founder, Cambridge China Bridge · 3 min read · Updated 2026-10-14

Someone working through invoices at a desk with a calculator and cash

Agree the baseline before negotiating

Save a dated baseline approved by purchasing and finance. Use the previous paid price for the same specification and comparable order terms where available. For a new product, agree a credible comparison basis and label savings against that basis explicitly. An inflated opening offer is weak evidence of a spending reduction. Use supplier quote comparison to check comparability. For advertised retail savings, see our guide to was-now discounts on imported stock.

Freeze the buying basket: product references, specification revisions, quantities and product mix. Record packaging, inspection scope, currency, delivery terms, payment terms and included charges. Compare the baseline and negotiated prices using that same basket. Keep this planned comparison separate from the savings actually delivered on purchases.

Give every saving a clear status

Use separate reporting categories rather than adding every negotiation result together. The Government Efficiency Framework says achieved savings should already have been realised. Apply that principle as a practical reporting discipline, and agree your own evidence gate with finance. Use factory negotiation guidance when agreeing the price and terms.

Suggested savings register statuses
StatusEvidenceReporting treatment
Offer onlyRevised quote without an accepted orderPotential saving, excluded from realised totals
CommittedSupplier-accepted order showing the agreed reductionTrack pending delivery and payment
RealisedAccepted goods, reconciled invoice and completed paymentInclude the verified net reduction
Avoided increaseDocumented proposed increase that was withdrawn or reducedReport separately from reductions against the baseline
UnresolvedMissing records, disputed charges or unsettled creditsExclude pending reconciliation

Trace the reduction through the transaction

Create a register linking each product line to the baseline document, negotiated quote, supplier acceptance, purchase order, goods acceptance record, final invoice and payment evidence. Record the price effective date and specification revision. Ask whoever claims the saving to identify the supporting documents, rather than submitting only a negotiation summary.

Match ordered, delivered, accepted, invoiced and paid quantities. Treat deposits and unpaid balances as pending. Check that the invoice applies the agreed unit price and that bank payments reconcile after fees and currency conversion. Resolve shortages, rejected goods and extra charges before closing the saving. Require evidence that any credit was refunded or applied to a paid invoice.

Calculate the net result without changing the basket

For each completed, comparable product line, subtract the final paid unit price from the baseline unit price and multiply by the accepted quantity covered by that payment. Include price increases as well as reductions when totalling the basket. Deduct additional costs incurred to obtain the saving. Apply the same allocation method to shared costs in both comparisons. For a logistics example, see our guide to evaluating port warehouse unloading savings.

Show negotiated product-price savings separately from exchange-rate movements, freight changes and changes in buying volume or product mix. Use a common currency basis to isolate negotiation, then reconcile to actual cash paid. A cheaper material or reduced inspection scope needs a separate comparison. Use budgeted versus actual landed costs to explain the wider spending difference.

Working out your own order? Send us the product on WhatsApp and we reply the same working day: WhatsApp us

Close the claim with finance

Give finance the fixed-basket comparison, transaction register and unresolved-items list. Record the reporting period, calculation method, exclusions and reviewer approval. Count a reduction only where its documents meet the agreed evidence gate. Keep future-volume projections separate, and prevent the same discount being claimed again as a rebate.

Leave conditional rebates pending until the conditions and settlement are evidenced. See annual volume rebates for agreeing those terms. With Cambridge China Bridge, ask the China staff to collect factory acknowledgements and specification confirmations, then match them to the order and invoice issued by your seller.

Frequently asked questions

Does a lower factory quote count as a saving?

Record it as a potential saving. For this method, it becomes realised only when a comparable accepted order leads to accepted goods and a reconciled, paid invoice.

Is stopping a supplier price rise a saving?

Record the documented avoided increase separately. If the final paid price also falls below your agreed baseline, report that reduction separately without counting it again.

How do I measure savings when quantities change?

Keep the fixed basket for comparing negotiated prices. Calculate realised savings using comparable accepted quantities covered by completed payments, and show volume and product-mix changes separately.

What documents should a sourcing company provide?

Ask for the baseline, revised quote, supplier acceptance, order, specification confirmation, goods acceptance record, final invoice and payment reconciliation, plus settled credits and extra charges.

Sources

  1. HM Treasury: The Government Efficiency Framework

Monthly email

What changed for UK buyers from China, and when to act

One email at the start of each month. Every figure has an official source.

One email a month. Unsubscribe with one click. Privacy

Discuss your sourcing project

Tell us the product, quantity and destination. Our own staff in China verify factories, follow production and inspect before shipment. We reply the same working day to confirm receipt and arrange next steps.

Discuss your sourcing project
Get a quote