Sourcing gas turbine stator vanes from China
Gas turbine stator vanes from China carry 0% UK duty across the relevant parts lines of heading 8411. Match the code to the engine application and vane specification; the manufacturer must check conformity assessment requirements for the product and its components. Cambridge China Bridge sources gas turbine stator vanes.

Duty and the stator-vane parts codes
Heading 8411 covers turbojets, turbopropellers, other gas turbines and their parts. Stator vanes are stationary guide components, so distinguish them from rotating blades. Code 8411 99 00 45 covers specified stationary-turbine guide blades made from nickel-based superalloys, operating above 600 kelvin but not above 1600 kelvin, with length no greater than 500 mm, width no greater than 900 mm and height no greater than 1300 mm.
Read from the UK Trade Tariff on 4 October 2026, all the selected parts lines carried 0% duty for goods from China. The supplied tariff record lists no anti-dumping or countervailing duty, suspension or attached import control for these lines. Turbojet and turbopropeller vanes have separate parts codes. Elsewhere in this heading, turbocharger wheel and housing lines carry a supplementary-unit import measure; if importing those alongside vanes, confirm the declaration requirement with your customs broker.
Confirm the commodity code using the engine application, drawing, alloy, operating temperature and dimensions. Do not select the specific stationary-turbine line merely because the invoice says turbine vane. For related components and wider heading context, see gas turbine rotor blades.
| Goods | Commodity code | Duty | Anti-dumping or countervailing duty on China |
|---|---|---|---|
| Stationary gas turbine guide vanes meeting the specified alloy and dimensional limits | 8411 99 00 45 | 0% | None |
| Other gas turbine stator vanes outside the specific guide-blade description | 8411 99 00 99 | 0% | None |
| Turbojet or turbopropeller vanes for the specified aircraft fitting category | 8411 91 00 20 | 0% | None |
| Other turbojet or turbopropeller stator vanes | 8411 91 00 90 | 0% | None |
Specify the vane stage, alloy and cooling geometry
Give the factory the engine model, stage, part number, drawing revision and whether you need individual vanes or vane segments. Specify the aerofoil profile, throat area, platform and mounting features, datum system and dimensional tolerances. State the alloy, casting structure, heat treatment, coating system and cooling-hole geometry. Identify any permitted repair or weld work explicitly.
Agree material certificates linked to casting batches, dimensional reports, crack-detection methods and acceptance criteria. Ask for coating and cooling-flow results where relevant. The manufacturer is responsible for checking conformity assessment requirements for the product and its components. Ask for that assessment for the intended application rather than treating a generic CE certificate as proof of vane suitability.
Worked duty example
Illustrative example, not a quote: Illustrative order: 40 stationary gas turbine stator vanes meeting this tariff description under 8411 99 00 45, invoiced at £28,000 free on board, with £4,000 of freight and insurance to the UK. The customs value is £32,000. Duty at 0% is £0. Import VAT at 20% is charged on the customs value plus duty, £32,000, so it is £6,400. With no duty, the only import tax is the VAT, which a VAT-registered importer can usually reclaim. The import duty and VAT guide explains each step.
Inspection checklist
Identity: match part markings, stage, drawing revision and batch records to the purchase order and material certificates.
Geometry: check the aerofoil profile, throat area, platform alignment and mounting features against the agreed datums and tolerances.
Integrity: review alloy and heat-treatment records, crack-detection results, coating coverage and cooling-passage cleanliness against the agreed acceptance criteria.
Arrival: check for chipped edges, damaged coatings, moisture and mixed batches. Keep each vane linked to its reports. Use the quality inspection guide to plan the checks.
Working out your own order? Send us the product on WhatsApp and we reply the same working day: WhatsApp us
What goes wrong
A vane can fit its mounting while having the wrong throat area or cooling geometry. Alloy substitution, blocked cooling holes, coating over holes, casting defects and unapproved repairs are failure points to check. A dimensionally acceptable sample does not establish the production batch's material or thermal performance.
Separate receipt inspection from permission to install. Have the turbine engineering team review the records and fit before installation. HSE states that plant and equipment must be made safe before maintenance starts. Resolve missing batch records or failed checks before fitting the vanes; factory verification can help establish which casting, coating and inspection processes the supplier actually performs.
Cambridge China Bridge sources these products for UK businesses, checking the factory and the documents before shipment. See factory verification. For machinery and equipment, see machinery imports.
Frequently asked questions
What is the UK import duty on gas turbine stator vanes from China?
The relevant parts lines in heading 8411 carried 0% duty on 4 October 2026. The supplied tariff record lists no anti-dumping or countervailing duty for these lines.
Which commodity code covers stationary gas turbine stator vanes?
8411 99 00 45 covers guide blades meeting its alloy, temperature and size conditions. Other vanes may fall under 8411 99 00 99. Confirm against the full specification.
Does a CE certificate prove a stator vane is suitable?
Check the manufacturer's conformity assessment for the intended application. Also obtain drawing-specific dimensional, material, coating and cooling records; a generic certificate does not establish fit or performance.
What should I ask a Chinese stator-vane factory for?
Ask for casting-batch traceability, alloy and heat-treatment records, dimensional reports, crack-detection results and relevant coating and cooling-flow results. Agree acceptance criteria before production.