The selected fan assembly and complete centrifugal fan lines carry 2% UK duty from China. A loose impeller needs its own classification check; the supplied tariff extract does not establish a general impeller code. Assess safety changes when fitting replacements. Cambridge China Bridge sources centrifugal fan impellers.

Written by Bono Xu, Founder, Cambridge China Bridge · 4 min read · Updated 2026-10-04

Aisles of a large supermarket seen from above, shelves fully stocked

Duty and the distinction between parts and fans

Read from the UK Trade Tariff on 29 September 2026, the selected lines under heading 8414 carry 2% duty for goods from China. They show no anti-dumping or countervailing duty, suspension or attached import control. The heading covers fans and their parts alongside pumps, compressors and other equipment.

The table distinguishes a narrowly described fan assembly from complete centrifugal fans. It is not a list of interchangeable loose-impeller codes. The assembly line requires aluminium-magnesium alloy, the specified dimensions and construction, and use in motor manufacture. The supplied extract does not contain a general residual fan-parts line, so it cannot settle the code for an ordinary replacement impeller.

Give your customs broker the drawing, material, intended equipment and details of everything supplied together. Confirm the commodity code before ordering. For complete equipment and the wider category, see industrial air blowers.

UK duty on these lines for goods of Chinese origin (one code per row), read from the UK Trade Tariff on 29 September 2026.
GoodsCommodity codeDutyAnti-dumping or countervailing duty on China
Aluminium-magnesium fan assemblies for motor manufacture, specified type8414 90 00 152%None
Other complete centrifugal fans, rather than loose impellers8414 59 35 902%None
Complete centrifugal blowers for vehicle battery module cooling8414 59 35 402%None
Complete direct-current centrifugal fans meeting the specified description8414 59 35 502%None

Specify the wheel, hub and operating duty

State whether the blades are forward-curved, backward-curved or radial. Supply a controlled drawing showing outside diameter, width, inlet opening, backplate, hub, bore, keyway and mounting features. Define rotation as viewed from a named side. Specify alloy or steel grade, thickness, weld construction, coating and the mating shaft fit.

Agree operating speed, temperature, air conditions, balancing acceptance and the test arrangement. Ask for balance records traceable to the supplied wheels. For replacement work, HSE says changes to machinery design, function or safety must be assessed. Have the equipment designer review changes in blade geometry, material or operating speed before installation.

Worked duty example

Illustrative example, not a quote: Illustrative batch of 40 fan assemblies meeting this line's full description under 8414 90 00 15, invoiced at £6,000 free on board, with £900 of freight and insurance to the UK. The customs value is £6,900. Duty at 2% is £138. Import VAT at 20% is charged on the customs value plus duty, £7,038, so it is £1,407.60. Import taxes total £1,545.60; a VAT-registered importer can usually reclaim the VAT, so the lasting cost is the £138 of duty. The import duty and VAT guide explains each step.

Inspection checklist

Geometry: measure blade profile, wheel diameter, width, bore and keyway against the approved drawing; check rotation and trial-fit the hub to a representative shaft.

Construction: compare material records with the order; examine welds, blade roots and backplates for cracks, distortion, sharp edges and coating defects.

Balance: match each available balancing record to the wheel identification and agreed test conditions. Check run-out and use a guarded assembly for any agreed running test.

Arrival: check for bent blades, displaced balance weights, hub corrosion and packing contact marks before installation. Record damage and keep affected wheels separate. See quality inspection.

What goes wrong

A wheel can fit the shaft yet perform poorly because its blade angle, inlet opening or rotation differs from the approved design. Bore errors cause difficult assembly or movement on the shaft; distorted backplates and damaged balance weights can cause vibration. Approve the drawing and a fitted sample rather than relying on catalogue photographs.

Packing that loads the blade tips can distort an otherwise acceptable wheel. Support the hub or backplate and keep wheels from touching each other. Agree how dimensional, balance and transit defects will be recorded and resolved before shipment.

Cambridge China Bridge sources these products for UK businesses, checking the factory and the documents before shipment. See factory verification.

Frequently asked questions

What is the UK import duty on centrifugal fan impellers from China?

The selected fan assembly and complete centrifugal fan lines carry 2%. The supplied extract does not establish the code for a general loose impeller; confirm its classification before applying that rate.

Can I use the complete centrifugal fan code for a loose impeller?

Do not assume so. The extract distinguishes fan parts from complete fans. Give your broker the drawing, intended use and contents of the shipment.

What should I ask for in an impeller balancing report?

Ask for wheel identification, the balancing method, test conditions, measured results and acceptance against your agreed specification.

Can I change the blade design of a replacement impeller?

Have the equipment designer review the change. HSE says changes to machinery design, function or safety must be assessed; matching the shaft bore alone does not establish suitability.

Sources

  1. UK Trade Tariff — commodity codes and duty
  2. HSE: Refurbished and modified machinery

Monthly email

What changed for UK buyers from China, and when to act

One email at the start of each month. Every figure has an official source.

One email a month. Unsubscribe with one click. Privacy

Discuss your sourcing project

Tell us the product, quantity and destination. Our own staff in China verify factories, follow production and inspect before shipment. We reply within one working day to confirm receipt and arrange next steps.

Discuss your sourcing project
Get a quote