Chinese New Year 2027: Date (6 Feb) and Factory Closures
Chinese New Year 2027 is 6 February. Mainland China’s statutory Spring Festival days are 5–8 February. Official guidance says the adjusted break can join a weekend to give 9 consecutive days in 2027; the final annual arrangement remains unconfirmed. Confirm factory closure, production recovery and shipping dates with your supplier.
Buying from China for a business? How our UK China sourcing agent service works · China sourcing agent for repeat and full-container programmes

The 2027 dates
The Hong Kong Observatory’s calendar confirms that Chinese New Year’s Day, the first day of the first lunar month, falls on 6 February 2027. New Year’s Eve is 5 February.
Mainland China’s national holiday regulations provide 4 statutory Spring Festival days: New Year’s Eve and the first 3 days of the lunar year. These correspond to 5–8 February in 2027. They are distinct from the longer break formed through weekends and adjusted working days.
The published general principle provides an 8-day adjusted Spring Festival break starting on New Year’s Eve, subject to exceptions. An official explanation specifically identifies 2027 as a year when adjoining a weekend can produce 9 consecutive days off. No State Council General Office notice finalising the 2027 arrangement was found in this audit on 20 October 2026; the exact holiday dates and make-up working days remain unconfirmed here.
For purchasing, record the factory’s actual closure and production recovery dates alongside the public holiday. See the Chinese New Year 2027 planning overview.
| Date or period | Status | What UK buyers should do |
|---|---|---|
| 5 February 2027 | Confirmed calendar date: New Year’s Eve | Do not assume production or collection remains available until this date. |
| 6 February 2027 | Confirmed calendar date: Chinese New Year’s Day | Use this as the holiday reference date, rather than an order deadline. |
| 5–8 February 2027 | Statutory days under the current mainland China regulations | Distinguish these days from the complete public holiday arrangement. |
| 8-day general principle; scope for 9 consecutive days in 2027 | Official explanation identifies the weekend extension; the final 2027 arrangement was not found | Check the State Council General Office annual notice for exact dates and make-up working days. |
| Factory wind-down and closure | Supplier-specific; may begin before the public holiday | Obtain written dates for final production, inspection and collection. |
| Factory reopening and full production | Supplier-specific; recovery may continue after the public holiday | Confirm your order’s production slot and dispatch date separately. |
Why factory disruption can extend beyond the holiday
DHL’s guidance describes disruption before and after the public holiday, including workers travelling home and a gradual return to production. Reopening alone does not confirm readiness for your order.
DHL also identifies pre-holiday freight capacity pressure, possible cost increases and quality risks from rushed production. Its restart guidance discusses recruitment, training, machinery checks and supplier readiness. These are planning risks, rather than a nationwide factory schedule for 2027.
Do not use these historical examples to assign a universal January shutdown or March recovery date. Ask for your supplier’s own schedule. Read when Chinese factories reopen after New Year and quality risks after Chinese New Year.
Order cut-offs by shipping mode
Calculate your order deadline from the required UK delivery date. Allow for production, inspection, possible rework, collection, transport and customs clearance; obtain estimates for your specific goods and route.
Ask the factory to confirm when finished goods will be ready, then ask the carrier or forwarder to confirm booking, cargo acceptance and documentation deadlines. Obtain transport confirmation separately from the factory’s dispatch promise.
Use Chinese New Year shipping cut-offs by mode for the detailed checks. Until production and collection are confirmed, allow for post-holiday dispatch in your plan. Do not rely on faster transport to compensate for unfinished production.
What to do now
Approve pre-production samples and written specifications before production. Schedule pre-shipment inspection with time for any necessary corrections.
Request written confirmation of the supplier’s last order-acceptance date, material availability, final production date, closure period, reopening date and your order’s production slot. Use the supplier planning message templates to request these details.
For stock purchases, assess demand and existing UK stock before increasing quantities. Plan stock coverage around the supplier’s confirmed closure and recovery schedule; see what to order before Chinese New Year. For an individual purchase, confirm whether the item is physically in stock or still needs manufacturing.
Check the first post-holiday production against the approved sample and specification, particularly where workers or production arrangements have changed.
For a smaller purchase, confirm stock location and collection availability. For a larger programme, record production and shipment milestones for each batch.
If a deadline is already tight, request a revised written schedule before paying or increasing the order. Agree what happens if the goods cannot pass inspection and leave before the closure.
Frequently asked questions
What date is Chinese New Year 2027?
It falls on 6 February 2027, the first day of the first lunar month. New Year’s Eve is 5 February.
How long is the Chinese New Year holiday in 2027?
Mainland China has 4 statutory Spring Festival days. Official guidance identifies scope for 9 consecutive days off in 2027 by adjoining a weekend to the adjusted break. The final annual arrangement was not found in this audit on 20 October 2026.
When will my Chinese factory stop taking orders?
Ask the supplier for its last acceptance date for an order that can complete production, inspection and collection before closure. Use its written schedule rather than a general holiday date.
Can I rely on full production returning as soon as the holiday ends?
Do not assume so. Ask when the relevant production line, workers and materials will be ready, and obtain a production slot for your order.
What is my last order date if I need the goods in the UK before the holiday?
Calculate it from your required UK delivery date using confirmed production and transport schedules. Include inspection, possible rework and clearance; obtain confirmation for your specific order.
Will paying for air freight or express solve a late order?
Ask for a revised delivery estimate based on cargo readiness, available capacity and acceptance conditions. Do not assume faster transport will compensate for unfinished production or failed inspection.
I only need a small personal order. Should I still check the closure dates?
Yes. Ask whether the goods are already made, where they are held and when collection is available. Confirm the relevant factory or warehouse schedule.
Sources
- Hong Kong Observatory: Gregorian–lunar calendar conversion table for 2027
- State Council: national holiday regulations, including the 4 statutory Spring Festival days
- China Government website: general principle of an 8-day adjusted Spring Festival break, subject to exceptions
- Beijing Government website, carrying Xinhua’s official policy explanation: scope for 9 consecutive days off in 2027
- DHL: Chinese New Year freight pressure, costs and pre-holiday quality risks; general guidance, not a UK route quotation
- DHL: post-holiday factory restart and gradual production recovery; 2026 guidance, not a 2027 schedule