Mould bases from China carry 0% UK import duty under 8480 20 00 00. The key customs rule is to distinguish the base from a complete mould; if buyer-provided tooling is left in China, ask your customs broker whether it affects the customs value of the parts it produces. Cambridge China Bridge sources mould bases.

Written by Bono Xu, Founder, Cambridge China Bridge · 4 min read · Updated 2026-10-17

Aisles of a large supermarket seen from above, shelves fully stocked

Mould-base duty and classification

Heading 8480 covers mould bases alongside complete moulds, moulding boxes and patterns. Mould bases have their own line, 8480 20 00 00. The table includes complete moulds as classification comparisons, rather than separate mould-base categories. See the wider moulds and tooling guide.

Read from the UK Trade Tariff on 17 October 2026, mould bases from China carried 0% duty. The supplied tariff record lists no anti-dumping or countervailing duty, suspension or attached import control for this line. HMRC requires transport, insurance, loading and handling costs connected with delivery to the UK border to be included in customs value.

Confirm the commodity code using the assembly drawing and a precise description of what is supplied. If buyer-provided tooling remains in China to produce imported parts, ask your customs broker whether its cost not already included in the seller's price should be added to those parts' customs value, and consult the wider tooling guide.

UK duty on these lines for goods of Chinese origin (one code per row), read from the UK Trade Tariff on 17 October 2026.
GoodsCommodity codeDutyAnti-dumping or countervailing duty on China
Mould bases8480 20 00 000%None
Complete injection or compression moulds for rubber or plastics8480 71 00 000%None
Other complete moulds for rubber or plastics8480 79 00 000%None
Complete injection or compression moulds for metal or metal carbides8480 41 00 000%None

Specify the plate stack and machine interfaces

Provide an approved assembly drawing showing plate order, overall dimensions, steel grades, hardness, flatness, parallelism and hole positions. State whether the base is supplied with insert pockets machined or left for your toolroom, and identify the drawing revision on the order.

Specify guide pillars and bushes, ejector plates and travel, return pins, support pillars, locating ring and clamping interfaces where fitted. Check compatibility with the intended moulding machine. Agree interchangeable spare components, rust protection, lifting arrangements and how the plates will be secured for transport.

HSE's work-equipment guidance places duties on people and companies that own, operate or control work equipment. Plan safe handling and installation of the base as part of the tooling assembly.

Worked duty example

Illustrative example, not a quote: An illustrative batch of machined mould bases for a small toolroom under 8480 20 00 00, invoiced at £5,000 free on board, with £2,000 of freight and insurance to the UK. The customs value is £7,000. Duty at 0% is £0. Import VAT at 20% is charged on the customs value plus duty, £7,000, so it is £1,400. With no duty, the only import tax is the VAT, which a VAT-registered importer can usually reclaim. The import duty and VAT guide explains each step.

Inspection checklist

Material: match steel certificates and measured hardness to the specified plate grades; trace the records to the supplied base.

Geometry: measure plate thickness, flatness, parallelism, pocket dimensions and hole positions against the approved drawing, including mating faces.

Movement: check pillar alignment, bush fit and ejector movement through the agreed travel; look for binding, excessive play and interference.

Arrival condition: inspect for rust, damaged edges, loose plates and missing components; photograph the base and reconcile its identification with the inspection report.

Working out your own order? Send us the product on WhatsApp and we reply the same working day: WhatsApp us

What goes wrong

A base can match the overall dimensions yet fail to fit the tool or machine. Misplaced holes, incorrect locating features and insufficient ejector clearance create rework. Poor plate parallelism or pillar alignment can make the assembly bind, while unsuitable steel or hardness can shorten service life.

Approve the assembly drawing before machining and request a dimensional report before dispatch. Check packing that prevents plate movement and protects machined faces. Record defects before altering the base so the supplier can assess the original condition.

Cambridge China Bridge sources these products for UK businesses, checking the factory and the documents before shipment. See factory verification. For machinery and equipment, see machinery imports.

Frequently asked questions

What is the UK import duty on mould bases from China?

The supplied tariff record shows 0% duty under 8480 20 00 00, with no anti-dumping or countervailing duty.

Is a mould base classified like a complete injection mould?

Mould bases have their own tariff line. Confirm what the shipment contains using the assembly drawing; a complete injection mould has a different line.

What should I put on a mould-base drawing?

Plate order, dimensions, steel grades, hardness, machining tolerances, guide components, ejector travel and machine interfaces, with a clearly identified revision.

What if the mould base stays at the Chinese factory?

If buyer-provided tooling produces your imported parts, ask your customs broker whether its cost not already included in the seller's price must be included in their customs value. Keep the tooling invoice and apportionment records.

Sources

  1. UK Trade Tariff — commodity codes and duty
  2. Valuing imported goods using Method 1
  3. HSE work-equipment regulations overview

Monthly email

What changed for UK buyers from China, and when to act

One email at the start of each month. Every figure has an official source.

One email a month. Unsubscribe with one click. Privacy

Discuss your sourcing project

Tell us the product, quantity and destination. Our own staff in China verify factories, follow production and inspect before shipment. We reply the same working day to confirm receipt and arrange next steps.

Discuss your sourcing project
Get a quote