Corrugated boiler furnace tubes imported from China as dedicated boiler parts carry 0% UK duty, with no anti-dumping or countervailing duty listed. Confirm the component's conformity assessment requirements against its intended use before ordering. Cambridge China Bridge sources corrugated boiler furnace tubes.
Buying from China for a business? How our UK China sourcing agent service works · China sourcing agent for small orders and first imports

Duty on corrugated boiler furnace tubes
Heading 8402 covers steam and other vapour generating boilers, superheated water boilers and their parts. For a separately supplied corrugated furnace tube dedicated to such a boiler, the parts line is the starting point for classification. The complete-boiler rows provide comparison; they do not describe separately imported furnace tubes.
Read from the UK Trade Tariff on 1 October 2026, all supplied lines carried 0% duty for goods from China. The data lists no anti-dumping or countervailing duty, suspensions or attached import controls. Import VAT is normally 20%.
Confirm the commodity code with your customs broker using the drawing, intended boiler and condition supplied. For related boiler parts, see replacement steam boiler tube bundles.
| Goods | Commodity code | Duty | Anti-dumping or countervailing duty on China |
|---|---|---|---|
| Boiler parts, including dedicated corrugated furnace tubes | 8402 90 00 00 | 0% | None |
| Complete firetube boilers, for comparison | 8402 19 10 00 | 0% | None |
| Complete other vapour generating boilers, for comparison | 8402 19 90 00 | 0% | None |
| Complete superheated water boilers, for comparison | 8402 20 00 00 | 0% | None |
Specify the corrugation and tubeplate interfaces
Supply the boiler drawing and identify whether this is a replacement furnace or a component for new fabrication. Specify material grade, design pressure and temperature, overall length, corrugation pitch and depth, diameter at crests and troughs, minimum wall thickness after forming, straight end lengths and weld preparations. Have the boiler designer or repair engineer agree the drawing before manufacture.
Agree the forming method, longitudinal seam position, welding procedures, heat treatment where specified and examination plan. Request material certificates traceable to the finished furnace, weld examination reports and dimensional records. Include support locations and transport bracing in the packing drawing.
For supply into Great Britain, components can require individual conformity assessment and marking, while many products use a marking covering the overall product. Spare parts can follow the conformity assessment requirements applicable when the original equipment was placed on the market. Establish the applicable route and document the intended replacement use before ordering.
Worked duty example
Illustrative example, not a quote: One replacement corrugated boiler furnace tube; illustrative order under 8402 90 00 00, invoiced at £13,000 free on board, with £4,000 of freight and insurance to the UK. The customs value is £17,000. Duty at 0% is £0. Import VAT at 20% is charged on the customs value plus duty, £17,000, so it is £3,400. With no duty, the only import tax is the VAT, which a VAT-registered importer can usually reclaim. The import duty and VAT guide explains each step.
Inspection checklist
Geometry: check corrugation pitch, depth, roundness, straight ends and overall length against the agreed drawing, both before shipment and on arrival.
Wall thickness: review the agreed thickness survey after forming, especially at crests, troughs and transitions; compare the results with the drawing's minimum thickness.
Materials and welds: match material identification to certificates and finished-component records; check seam locations, weld examination coverage and recorded repairs.
Arrival condition: inspect for flattened corrugations, dents, corrosion and damaged weld preparations. Compare with dispatch photographs and quarantine discrepancies before installation.
Working out your own order? Send us the product on WhatsApp and we reply the same working day: WhatsApp us
What goes wrong
A furnace can match the overall diameter but have the wrong corrugation profile or straight end length. Forming can leave locally thin areas, and transport damage can distort the ends needed for tubeplate fit-up. Missing material identification or weld records can prevent the repair engineer from accepting an otherwise usable component.
Do not resolve a fit problem by trimming or reshaping without the repair engineer's agreement. Before using qualifying pressure equipment, a written scheme of examination must be in place and an examination undertaken. Ask the competent person to review the replacement plan and examination arrangements before returning the boiler to service.
Cambridge China Bridge sources these products for UK businesses, checking the factory and the documents before shipment. See factory verification. For machinery and equipment, see machinery imports.
Frequently asked questions
What is the UK import duty on corrugated boiler furnace tubes from China?
The supplied tariff data shows 0% duty under the boiler-parts line 8402 90 00 00, with no anti-dumping or countervailing duty listed. Confirm that your furnace tube qualifies as a dedicated boiler part.
Does a replacement furnace tube need CE or UKCA marking?
Confirm the component's applicable route. Components can require individual assessment and marking; many products use overall marking. Spare parts can follow the original equipment's conformity assessment requirements.
What drawing details should I send to the factory?
Include material, design conditions, corrugation pitch and depth, crest and trough diameters, minimum formed wall thickness, straight end lengths and tubeplate weld preparations.
Can I install the furnace tube as soon as it arrives?